How much does it cost to renovate a 3 bed house in London?

Costs
Planning and budgeting
Mid-level renovation of a 93 m² London 3 bed house costs £73k to £143k including VAT, before fees

A mid-level renovation of a typical 3 bed house in London costs about £73,000 to £143,000 including VAT. That buys a new kitchen and bathroom, a partial rewire, replastering and redecorating throughout. A cosmetic refresh runs £22,000 to £59,000, a full strip back to brick £186,000 to £260,000, and adding a side return takes you past £229,000.

Those totals assume a 93 m² house, which is the government's space standard for a two-storey, three-bedroom, five-person home. Floor area is the first number to pin down, because everything else gets multiplied by it.

How big is a typical 3 bed house in London?

Most cost guides quietly assume a 90 m² semi somewhere outside London, then bolt on "30 to 40%" for the capital. That is two guesses stacked on top of each other. Start with the size of the house instead.

Measure

Floor area

Source

Space standard, 3 bed, 5 person, two storeys

93 m²

MHCLG, March 2015

Three-bed terraced houses, across age bands

79 to 93 m²

English Housing Survey, 2012 data

All pre-1919 homes in England

105 m² average

English Housing Survey, 2012 data

All homes in London

84 m² average

English Housing Survey 2018-19

Median house in England, EPC floor area

88 m²

ONS, October 2022

So 93 m² is a fair middle for a two-storey London 3 bed. A taller Victorian with a full-height back addition can reach 110 to 120 m², and that alone adds a fifth to a third to every total below. Your EPC lists a total floor area, so check it before you compare anyone's per m² rate with your house.

What does each level of renovation cost?

Here is the same 93 m² house at four depths of work. Every figure includes VAT at 20% and excludes professional fees, which come later.

Level

What it includes

London per m²

3 bed at 93 m²

Cosmetic refresh

Decorating, flooring, internal doors, lighting, making good. No new services

£240 to £630

£22,000 to £59,000

Mid-level renovation

All of that, plus new kitchen, new bathroom, partial rewire, replastering where needed

£780 to £1,540

£73,000 to £143,000

Full strip back

Back to brick: full rewire, replumb, new heating, replaster, windows and floors

£2,000 to £2,800

£186,000 to £260,000

Strip back and extend

Full strip back plus a 12 to 20 m² side return extension

Not a per m² job

£229,000 to £380,000

The first two rows take BestBuilders' 2026 bands for a 3 bed, which state they include VAT, and apply its 20 to 40% London uplift. The strip back row is the London and South East band from our renovation cost guide and calculator. BestBuilders' London-adjusted figure for the same work is lower, about £1,320 to £2,520 per m², but period London houses rarely strip back cheaply, so we plan on the higher band. The final row adds the £43,000 to £120,000 side return range from our extension guide.

Our own project data is a useful sense check. Beams estimates for projects between January and July 2026, all including VAT, came out at a median of £54,258 for a kitchen and bathroom, £79,138 for six to eight rooms and £112,557 for nine or more. A 3 bed house has seven to nine rooms once you count the hall and stairs, so a whole-house refurbishment that leaves the structure alone lands in the lower half of the mid-level band. Two independent sources agreeing is about as good as renovation numbers get.

Bar chart: London 3 bed renovation from £22k to £59k cosmetic up to £229k to £380k strip back and extend, inc VAT

What pushes a London 3 bed up the range?

Four things, roughly in order of how much they move the total.

The age of the house. Pre-1919 homes average 105 m² against 92 m² for English homes overall, so they are bigger before you start, and they hide more. Lath and plaster ceilings, lead supply pipes, no damp proof course and rotten joist ends under suspended floors all show up once the boards come up. Our guide to the problems that turn up in Victorian terraces goes through each one.

Structural changes. Opening up a kitchen and dining room nearly always means a load-bearing wall, and removing one with a steel beam runs £1,800 to £3,500 before the engineer and the party wall surveyor.

Your street and your borough. The London premium sits mostly in labour and access rather than materials. Steels come through the front door by hand and waste leaves the same way. Skip permits alone range from £37.60 in Wandsworth to £146 in Kensington and Chelsea, and why renovating in London costs more sets out the borough charges in full.

The kitchen. It is the single biggest line in most 3 bed budgets. Our median for a kitchen alone was £36,619 including VAT, and our kitchen renovation cost guide breaks that down by layout and component.

Get a number for your 3 bed

Floor area, age and scope decide the total. Get an estimate for your house before the first builder visits.

Do renovation prices include VAT?

They should, and plenty of guides do not say. Checkatrade's 3 bed table, which sits at the top of Google for this question, headlines £43,530 to £110,350 under a column labelled "Cost range (+VAT)", which leaves you guessing whether the VAT is in or still to come. On £100,000 of building work, that guess is worth £20,000.

Renovating an occupied home is standard-rated at 20%, on labour and on the materials your builder supplies. Two reliefs exist. If the house has been empty for two years or more before work starts, the renovation can qualify for 5% under HMRC VAT Notice 708. Converting a house into flats, or flats back into a house, also qualifies for 5% on the work involved.

The difference is large. On a £150,000 strip back priced before VAT, 20% adds £30,000 and 5% adds £7,500. Raise it before the builder prices the job, because the evidence needs to be in place before work starts.

What fees sit on top of the build cost?

Build cost is not project cost. On a 3 bed renovation these are the usual extras.

Fee

Typical cost

When you need it

Householder planning application

£548

Extensions, roof changes, external work in a conservation area. From 1 April 2026

Lawful Development Certificate

£274

Written confirmation that work is permitted development

Building control, extension up to 40 m²

£700 to £1,300 inc VAT

Inner London runs higher, up to £1,875.55 in Camden

Structural engineer

£550 to £1,500

Steel beams, chimney breast removal, extensions

Party wall surveyor

£900 to £1,400 plus VAT

Per neighbour, and a mid terrace has two

Architect or designer

3% to 15% of build cost

Drawings only at the bottom, full service at the top

Skip on the road

£1,133.28 for a fortnight in Camden

Licence, admin and bay suspension together

Then hold back 10% to 15% as contingency, and more on a house built before 1940. In a London terrace the party wall line is the one people forget to double, and our guide to party walls in London terraces explains why the rear neighbour can count too.

What does a mid-level renovation cost all in?

Take a 93 m² two-storey Victorian terrace. The plan is a mid-level renovation, with the kitchen and dining room knocked into one and the steel bearing on the party walls. Everything else stays in its current footprint.

Item

Low

High

Build, mid-level at 93 m², inc VAT

£73,000

£143,000

Load-bearing wall removal with steel

£1,800

£3,500

Structural engineer

£550

£1,500

Party wall surveyors, two neighbours, inc VAT

£2,160

£3,360

Designer, drawings only at 3% of build

£2,190

£4,290

Contingency at 15% of build

£10,950

£21,450

Total

£90,650

£177,100

Plan on roughly £91,000 to £177,000, plus your council's building control charge. On site that is around 16 to 22 weeks, and how long a full house renovation takes explains why the months before the build usually take longer than the build.

Is it worth renovating, or should you extend or move?

Keep the numbers next to the value of the house. HM Land Registry put the average London home at £545,579 in September 2026, down 3.5% on a year earlier, the weakest annual change of any region. A full strip back at £186,000 to £260,000 is a third to nearly half of that, so it needs a reason beyond new paint.

Space is usually that reason. Nationwide's October 2025 research found an extra double bedroom adds around 13% to the value of a two-bedroom house, and a bedroom plus a bathroom up to 24%. Our guide on whether a house extension adds value runs those figures against London build costs, and if you are weighing the alternative, is it cheaper to extend or move house puts stamp duty and agents' fees next to the build.

How Beams helps

Most 3 bed budgets go wrong before anyone picks up a tool, because three builders quote three different scopes. We pin down the scope and the specification room by room first, give you a realistic cost range, then line up to three vetted London builders to price exactly that.

You get one fixed price with staged payments held securely, released only when you approve each milestone, and a 12-month workmanship warranty when the job is done.

Common questions about renovating a 3 bed in London

How much does it cost per m² to renovate a house in London?
About £240 to £630 per m² for a cosmetic refresh, £780 to £1,540 for a mid-level renovation and £2,000 to £2,800 for a full strip back, all including VAT and before fees.

How much does it cost to fully renovate a Victorian terrace in London?
At 93 m², £186,000 to £260,000 including VAT before fees. A larger 120 m² terrace comes to £240,000 to £336,000 on the same rates.

Can you renovate a 3 bed house in London for £50,000?
You can refresh one, or redo the kitchen and bathroom. Our median for a kitchen and bathroom together was £54,258 including VAT. £50,000 will not cover rewiring, replastering and new services throughout.

Is it cheaper to renovate room by room?
Not noticeably on price. Our median for a kitchen and bathroom done together was within £424 of the two done separately. Phasing costs you a second round of disruption rather than a premium.

Do I need planning permission to renovate a 3 bed house?
Usually not for internal work on an unlisted house outside a conservation area. Building regulations still apply to structural changes, rewiring and new bathrooms. Extensions, roof alterations and external changes are where planning comes in.

Should I move out during a full renovation?
For a strip back, usually yes. Trades can work house-wide instead of room by room, which shortens the programme and often offsets the rent.

Where these figures come from

  • Floor areas: MHCLG, Technical housing standards, nationally described space standard (March 2015); English Housing Survey, Floor Space in English Homes (2018 report, 2012 data); English Housing Survey 2018-19, Size of English Homes fact sheet; ONS, admin-based property floor area statistics (October 2022, EPC data to March 2021).
  • Cosmetic and mid-level bands: BestBuilders, House Renovation Cost UK 2026 (cosmetic £200 to £450 per m², medium £650 to £1,100 per m², gut £1,100 to £1,800 per m², all stated as including VAT at 20%, with London 20 to 40% higher). London figures are those bands multiplied by 1.2 and 1.4.
  • Full strip back band and Beams project medians: Beams renovation cost guide, 2026 (medians across 7,491 project estimates, January to July 2026, including VAT).
  • Side return, fees, building control and party wall figures: Beams extension cost guide and London cost guide, which cite Planning Portal fees from 1 April 2026, council fee schedules and published surveyor price lists.
  • VAT: HMRC VAT Notice 708, Buildings and construction.
  • "Cost range (+VAT)" table: Checkatrade, House renovation cost breakdown 2026, read November 2026.
  • House prices: HM Land Registry, UK House Price Index, September 2026. Value uplift: Nationwide house price research, October 2025.

These are planning figures, not a quote. Your house, its condition and your specification set the real number.

Find out what your 3 bed will cost